Theory of Constraints Golden Nugget
#8 – When you say “red”, what do you mean?

(Production)

When we are told that a production company has 20% red orders, what does that mean? Seemingly the answer is clear – it means that if we go to the floor, we will see that 20% of the orders are red. But then again, maybe it means something else – that out of all the completed orders, 20% were finished while being red?

Here we have a situation where one term is being used to describe two different things. This ambiguity wouldn’t be a real problem if the practical implications, stemming from the two different interpretations, where the same. But this is definitely not the case; one of the above meanings of “red” is very important in terms of assessing the state of the operation, while the other has no practical implications and using it leads only to confusion.

In order to clarify the above statement, we ought to better understand the meaning of each definition. The first definition of red percentage is a description of a snapshot – the situation on the floor at a certain moment: how many orders from each color do the production workers see? Figure 1.a schematically shows a distribution of orders’ color on the floor at a specific point of time, under the assumption of a constant stream of incoming orders. The X axis is not a time axis, but rather represents the “age” of an order at the point of time when the snapshot was taken… Click here to continue reading.

Managing Production Priorities
Dr. Eliyahu M. Goldratt

Related Info
Share this video

In this extract from the Goldratt Webcast Series on Make to Availability (MTA), Goldratt presents and explains the strategy, tactics and corresponding assumptions for managing production priorities the TOC way.
17 min, English, Spanish

Tags: goldratt, Nuggets, Production, theory of constraints

This entry was posted on Wednesday, May 5th, 2010 at 11:27 AM and is filed under General. You can follow any responses to this entry through the RSS 2.0 feed. You can leave a response, or trackback from your own site.

Leave a Reply

Click here to cancel reply.

You must be logged in to post a comment.

« Theory of Constraints Golden Nugget
#7 – Minimum batch progression
Theory of Constraints Golden Nugget
#9 – Color Psychology
»
  • Subscribe

    • Entries (RSS)
    • Comments (RSS)
  • Archives


  • Calendar

    September 2010
    M T W T F S S
    « Jul    
     12345
    6789101112
    13141516171819
    20212223242526
    27282930  

  • Tags

    batch progression Buffer Management Change Clarke Ching Color Psychology DDP goldratt Interview Inventory Isn't It Obvious Judging change Lead Time MTA MTO Nuggets operations Organizational Change Production Production Buffer Resisting Change RRR S&T Tree strategy and tactics supply chain The Goal theory of constraints thinking processes toc viable vision warehouse

  • Categories

    • General
    • Nuggets

  • Meta

    • Log in
    • Entries RSS
    • Comments RSS
    • WordPress.org

Goldratt's Blog is proudly powered by WordPress
Entries (RSS) and Comments (RSS).